Gorton Foundry, Hammertone Road

Gorton Foundry, Hammertone Road

Gorton Foundry, Hammerstone Stone

PROJECT OVERVIEW

Hannan Associates are very pleased to be part of Morgan Sindall’s team involved in the refurbishment of Manchester City Council’s waste disposal and maintenance depot located at the old Gorton Foundry site on Hammerstone Road in Gorton, Manchester.

The site spans a total area of 3.80ha and the west side is dominated by a 10,000 sq m industrial unit, which was once occupied by railway manufacturers Beyer and Peacock who manufactured nearly 8,000 railway locomotives here from 1854 to 1966.

The unit is a single storey open plan building which will be remodelled and refurbished to provide a new multi-tenanted building with new office and maintenance facilities. The overall project also includes the rationalisation and amalgamation of services of other Manchester City Council depots at Ardwick and Newton Heath.

Our team are very pleased to be providing Building Services Design, Building Physics Design and Sustainability Services for the transformation of this interesting building.

Photovoltaic panels have been incorporated into the design to minimise carbon emissions related to building processes and vehicle charging. To augment this strategy a battery storage solution has been proposed to store renewable energy generated by the PV during peak periods, thus maximising carbon reduction and minimising the technologies payback period.

As part of the councils overall strategy to reduce greenhouse gas emission from their portfolio, the development has been designed using dynamic simulation to embed a fabric first approach into the carbon reduction strategy.  As part of the environmental performance of the development, it has been decided to install rainwater/grey water harvesting. This system will as a minimum feed the vehicle wash system to minimise the use of carbon intensive potable water .

Energy monitoring through the use of smart meters has become commonplace in the home to enable residents to minimise energy usage.  BEMS enables the building users and FM team monitor, benchmark and target energy consumption thus reducing the buildings carbon emissions on a system by system basis as well as a tenancy basis.

We are very pleased to be working for Manchester City Council and Morgan Sindall on this interesting project. We join Fletcher Rae Architects and Curtins Consulting on the project design team.

 

Historic Beyer & Peacock Site Refurb

 

 

About This Project

5

CLIENT : Morgan Sindall & Manchester city Council

5

ARCHITECT : Flecher Rae Architects

5

PROJECT VALUE : £12.2 million

5

CONTRACT DURATION: 2018 – ongoing

Get in touch

13 + 2 =

Paddington Village MSCP, Liverpool

Paddington Village MSCP, Liverpool

Paddington Village MSCP, Liverpool

PROJECT OVERVIEW

We are currently engaged to design a new 1245 space car park and retail unit at the Paddington Village development in Liverpool.

The scheme includes a 12 storey MSCP with sprinklers, fire fighting shafts with fire fighting lifts. Car park access is achieved by a triplex lift arrangement and a separate fire fighting lift.

The scheme to this site also includes interface with the adjoining new Energy Centre which provides district heating and private wire power to the wider Paddington development.

The Energy centre includes a Combined heat and power plant to reduce the carbon footprint of the scheme and provides private wire HV to the car park and LV essential power to serve the essential fire fighting services in the car park.

Paddington Village is a £1bn flagship expansion site within Liverpool’s Knowledge Quarter, which will be home to education, health, science and technology facilities as well as residential, hotel, leisure and retail.

 

Liverpool Paddington Village Car Park

 

About This Project

5

CLIENT : Morgan Sindall & Liverpool City Council

5

ARCHITECT : KKA

5

PROJECT VALUE : £10 million

5

CONTRACT DURATION: July 2017 – ongoing

Get in touch

11 + 2 =

Pin It on Pinterest