The Lodge, Newbury Racecourse

The Lodge, Newbury Racecourse

The Lodge, Newbury Racecourse

PROJECT OVERVIEW

We are Building Services, Sustainability/Renewable Energy and Utilities Engineering Services Consultants for the redevelopment of Newbury Racecourse.

The £20 M redevelopment includes a new 4* 120-bed hotel by ‘Bespoke’ Hotels.

The site will also have up to 1500 new homes of which up to 450 will be affordable, shared equity housing or available to rent.

Hannan Associates undertook the design of the mechanical and electrical services up to Stage E, for the new 36 bedroom Lodge hotel with canteen facilities, and a new Rocking Horse Nursery.

About This Project

5

CLIENT : Newbury Racecourse

5

ARCHITECT : KKA Architects

5

PROJECT VALUE : £20 million development

5

CONTRACT DURATION: August 2010 – ongoing

Get in touch

11 + 5 =

Bristol Sport Ashton Gate Stadium

Bristol Sport Ashton Gate Stadium

Bristol Sport Ashton Gate Stadium

PROJECT OVERVIEW

We were appointed by Bristol Sport together with Capita Project Management and KKA Architects for the scheme to complete the redevelopment of the Ashton Gate Stadium.

The redevelopment involves the replacement of the South Stand, West Stand and the refurbishment of the existing East Stand increasing seating capacity to circa 26,500 seats. Construction for the development has been phased to allow continued usage of the stadium for football and rugby events during the construction. The stadium is designed as a flexible use for non-event day use including exhibitions and conferences and the concourses have enhanced finishes with LED lighting and signage internally and externally.

The planning conditions included a requirement for renewable energy production and the scheme includes bio diesel heating and a large photovoltaic array on the West stand roof.

We were appointed to provide MEP Design, Acoustics, IT, Sports Lighting & Fire Engineering Consultancy and BREEAM Assessment for the project.

About This Project

5

CLIENT : Bristol Sport

5

ARCHITECT : KKA

5

PROJECT VALUE : £40 million

5

CONTRACT DURATION: April 2013 –2016

Get in touch

6 + 10 =