PROJECT OVERVIEW

One of several projects we have undertaken for MUFC during the last 25 years is the Old Trafford Museum that includes a visitor centre and the red café. We designed the complete mechanical, electrical and public health installations. The project involved the fitting out of the existing level 3 of the North Stand. Themed areas include the theatre, Red café and interactive exhibit spaces.

Designing the mechanical and electrical services for the building was a challenge due to the unique construction of the stadium and stringent requirements for public safety on Match and non-match days. Interfacing with existing systems was a major consideration during the design and installation. Existing systems had to be extended and/or modified so that they were coordinated with the exhibition stands and displays. All works were undertaken whilst the stand was occupied.

The museum won large visitor attraction of the year at the 2013 Manchester Tourism Awards, it has also been awarded an Enjoy England Quality Attraction Rose. It has achieved a Gold Green Tourism Status due to outstanding contributions to green tourism, including the use of latest technologies such as LED lighting, efficient boilers and renewable technologies.

Awards
2013 Manchester tourism Awards – large visitor attraction of the year
Enjoy England – Quality attraction rose
Green Tourism – Gold Award

About This Project

5

CLIENT : Manchester United Football Club

5

ARCHITECT : AFL

5

PROJECT VALUE : £4 million

Get in touch

14 + 7 =

Amazon, Logic Leeds Business Park

Amazon, Logic Leeds Business Park

Amazon, Logic Leeds Business Park

PROJECT OVERVIEW

We provided utilities infrastructure master planning and procurement for the overall development proposals and design and monitoring services for the MEP associated with the initial speculative 80,000 ft² industrial unit. As part of the team we contributed to the specification of the unit which was developed to provide a wide tenant appeal and a high level of flexibility to attract potential tenants.

The unit is now let to Amazon and we assisted the client during the letting of the unit and carried out the design and monitoring of additional car parking facilities requesting by Amazon.

Logic Leeds is part of the Leeds Enterprise Zone, which means that it benefits from a range of incentives for occupiers. Overall there is outline planning for 1.6 million ft² of quality industrial, storage and distribution development. All buildings will have a high BREEAM rating and state-of-the-art facilities.

About This Project

5

CLIENT : Muse

5

ARCHITECT : Fletcher Rae Architects

5

PROJECT VALUE : £5 million

5

CONTRACT DURATION: 2014 – 2016

Get in touch

6 + 7 =

John Lewis, Logic Leeds Business Park

John Lewis, Logic Leeds Business Park

John Lewis, Logic Leeds Business Park

PROJECT OVERVIEW

The building was constructed to meet the pre let requirements of John Lewis for a new 50,000 ft² customer delivery distribution hub. The building design and handover information was carried out using BIM protocols in accordance with John Lewis requirements.

Our role involved assisting the client with tenant liaison and the development of the brief with the John Lewis team. We were responsible for the infrastructure procurement and the provision of a Stage 3+ design and performance specification for the MEP systems. We monitored the contractor design stages and construction of the works through to handover to ensure compliance with the strict tenant requirements

Logic Leeds Business Park consists of a 100 acre manufacturing & distribution park located within the Aire Valley Enterprise Zone. The business park provides high quality industrial & warehouse units, in a fully landscaped environment, with immediate connectivity to the M1 motorway.

We are very proud to have been involved with the development of the entire Business Park as well as providing Tenant Liaison duties where required.

About This Project

5

CLIENT : Muse

5

ARCHITECT : Fletcher Rae Architects

5

PROJECT VALUE : £6.2 million

5

CONTRACT DURATION: 2015 – 2016

Get in touch

4 + 4 =

City of Manchester Stadium & Athletics Arena

City of Manchester Stadium & Athletics Arena

City of Manchester Stadium & Athletics Arena

PROJECT OVERVIEW

The City of Manchester Stadium was built for the Commonwealth Games held in Manchester during 2002 and converted to a football stadium for Manchester city following the games.

Hannan Associates provided checking duties and advice based on the wide experience gained in the design and execution of major stadia schemes. Hannans acted for the city council throughout all phases of the scheme. From design development, to installation and commissioning both for the commonwealth games and the occupation by Manchester City Football club. Hannan’s services also including the provision of on site engineers for the duration of construction and fitting out.

The engineers provided support for the building services maintenance contractors during the games including advice on problem solving. Part of the appointment was to identify deficiencies or over design in the scheme to provide value engineering advice to the design and build team.

Hannans were part of a team which included an architect and structural engineer; we worked together to provide a strategically coordinated design services approach.

Following the successful completion of the main scheme Hannan were appointed to design the building services for the Regional Athletics Arena and the management suite.

About This Project

5

CLIENT : Manchester City Council

5

ARCHITECT : Arup Associates

5

PROJECT VALUE : £112 million

5

CONTRACT DURATION: 2001 – 2004

Get in touch

10 + 1 =

Arena Central

Arena Central

Arena Central, Birmingham

PROJECT OVERVIEW

We are providing MEP Performance Duties, Site Infrastructure Services & BREEAM Assessment for Arena Central, Birmingham’s first speculative office scheme since the recession. It is a 9.2. acre mixed-use site being developed by Arena Central Developments LLP, a joint venture led by Kier.

Arena Central will deliver over 1 million sq ft of office-led mixed use development, alongside a unique public realm designed by Make Architects that features over 50 per cent soft landscaping.

  • 1 Centenary Square – a 210,000 sq ft, 10 storey, Grade A office building – HSBC Head officeNow Complete
  • No. 3 Arena Central – a 240,000 sq ft, 14 storey, Grade A office building pre-let to the UK GovernmentUnder Construction
  • 5 Centenary Square – 135,000 sq ft, 8 storey, Grade A office building – planning in place

We are very pleased to be working alongside Make Architects, Gillespies Landscape Architects, Arcadis and WSP on the design team and main contractor Galliford Try.

We also provided MEP support for Gillespie’s exciting public realm proposals for the development and MEP support for the alterations to the existing basement car park.

About This Project

5

CLIENT : Arena Central Developments

5

ARCHITECT : Make Architects

5

PROJECT VALUE : £400 million

5

CONTRACT DURATION: 2013 – ongoing